Last week DP CleanTech signed a contract agreement with Shaoneng Group for the delivery of two 30 MW biomass power plants near Shaoguan in South China and will be the 53rd and 54th biomass power plants delivered to the China market. The Shaoneng Project will use eucalyptus and wood residues to generate renewable electricity for the local community....
Dong Energy have awarded DP CleanTech the contract to supply the Superheaters for a coal to biomass conversion project in Studstrupvaerket, Denmark. The existing 350 MW coal-fired power plant is being converted to run on a very fine waste wood powder. DP CleanTech will deliver approximately 350 tons of Superheater parts, which include replacement o...
Dong Energy have awarded DP CleanTech the contract to supply the Superheaters for a coal to biomass conversion project in Studstrupvaerket, Denmark. The existing 350 MW coal-fired power plant is being converted to run on a very fine waste wood powder. DP CleanTech will deliver approximately 350 tons of Superheater parts, which include replacement o...
DP CleanTech has been awarded the contract to supply the Flue Gas Treatment system for Devon County Council’s (www.devon.gov.uk) first waste-to-energy power plant in Exeter. DP CleanTech has extensive experience in redefining complex requirements in order to deliver specialized solutions, and has a proven track record in delivering reliable a...
DP CleanTech is pleased to announce the appointment of Mr Andreas Asmussen as Managing Director and Head of Engineering, Europe, with effect from 2 February 2012. He will be located in DP CleanTech’s new HQ offices in Copenhagen, Denmark. The global expansion of DP CleanTech requires significant efforts to ensure continued integration and ...
DP CleanTech, a leading expert in biomass power, has set up a new European headquarters office in Herlev, Copenhagen. This newest facility represents the company’s 5th strategic investment in the last year, and is in response to the rapid development of the company and the biomass power industry. Employee numbers have increased si...
DP CleanTech has set up a new office in the UK. Based in Wolverhampton, this newest facility represents the company’s 4th strategic investment in the last year, and follows the recent opening of new offices and manufacturing facilities in Thailand and Poland. The UK is expected to be a promising market for DP CleanTech due to the lar...
DP CleanTech has been contracted to convert an ageing coal fired power plant to run instead on waste wood such as eucalyptus bark. The retrofitted plant will provide green electricity and steam to Thailand’s largest bioethanol plant which is currently being built by TPK. The new bioethanol plant, in Nakorn Ratchasima, is expected to produce 1...
On 20th – 21st August 2011 DP CleanTech hosted a biomass power and waste to energy conference at the Qingdao Beer festival. The conference was set up to explore China’s potential for further biomass power development as well as introducing waste to energy technology. During the morning of the first day DP CleanTech CEO,Simon Parker a...
DP CleanTech is rapidly building its operations in Poland, having recognized that high quality manufacturing and professional skills are readily available to support rapid growth in the global waste to energy industry. Only 18 months after DP Cleantech invested €1.5mill in a manufacturing facility inJędrzejów, the company is further ...